FOLLOW OUR PROGRESS
Keep up with our progress on this page. We will be updating it frequently.
project update - April, 2010
IPBRP has hired recognized bungalow authority Charles Shanabruch to do a value engineering review to make sure that the project is as cost effective as possible. Chuck founded the Historic Chicago Bungalow Assn. in 2000 which now has 8000 members. His passion for our project and his extensive experience in historic preservation and energy efficiency programs will be a tremendous asset to our endeavors.
List of Needed Materials
March, 2010 -
We have received a "wish list" of items needed for the project. All donors will be acknowledged in plaque form in the bungalow. This is a great opportunity for suppliers to get involved with this project by helping us defer some of the costs and at the same time receive a permanent marketing presence in this Green Bungalow Project.
Permeable Pavers - 1560 sf
Porous Concrete - 105 sf
Spray Foam Insulation Attic - 1920 sf
Spray Foam Insulation Basement - 1379 sf
Basement Windows - 7
Bamboo Floor and Sub Floor Main Room - 1825 sf
Basement Storage Units - 10
Microwave - 1
Refridgerator - 1
Computer - 3
Overhead Projection Unit - 1
Educational Kiosk - 1
Kitchen Sink refinishing - 1
Bathtub refinishing - 1
Low flow or dual flush toilet - 4
Low flow bathroom sink - 4
LED Exit Sign - 20
Low flow shower head - 1
Light fixtures - various kinds - recreate historic look - 35
inside work out for bid
February, 2010 -
The Chicago Park District is soliciting bids for the internal construction. Check the CPD web site.
ROOF REPAIR AND REPLACEMENT
January, 2010 -
Step One - The roof has been dismantled and replaced. Many of the original tiles were reused. Check out the photographs in our gallery.
Frequently asked questions
Answered by Brendan Daley
October 2, 2009
1) Do you have to replace the entire roof?
The roof has most of the original clay tile on it from when the Bungalow was constructed in the early 1920s. Until work begins on the roof, we will not be certain as to what portions of the clay tiles are reusable. However, one of the goals of green renovation is to reuse or recycle as many of the building materials as possible. Therefore, the project hopes to reuse tiles on the roof when possible, or elsewhere on site if not possible. The unusable tiles may be ground up to be used as fill material for the new accessible ramp entrance or other possible onsite uses. When tiles are not reusable or recyclable onsite, the contractor will be encouraged to find alternative uses for them with landfilling them only as a last resort.
2) What type of insulation will be installed?
The Bungalow, like many bungalows in Chicago, has very little or no insulation. In order to improve the energy efficiency of a building and thus reduce utility bills and increase indoor comfort, it is very important to add insulation. The project intends to insulate using spray foam insulation in the attic space and select wall areas. This type of insulation is sprayed into wall cavities or the attic and expands while it dries. The project intends to achieve an R-39 insulation value in the attic space. Additionally the windows will be repaired retrofitted with insulated double glazed windows.
3) Is the original flooring usable?
In the main room several layers of tile were placed on top of the original wood flooring. Like with the clay tiles, we will not be certain as to the condition of the original wood flooring until the tiles are removed. However, it is unlikely that the original wood floor will be usable. The project intends to use a sustainable wood flooring material in its place such as bamboo.
4) Will the basement be available for use?
The basement will continue to be a storage area as it is now and will not be available for use.
5) When do you think the project will be complete?
We are hopeful that the project will be completed in early summer 2010.
|